Contract No: HK/2015/01

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Works (Stage 3)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 , Fep-06/356/2009, FEP-07/356/2009 and Fep-08/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

-       June 2017 -


CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

July 2017

 

 


Table of contents

 

1      Introduction. 10

1.1        Scope of the Report 10

1.2        Structure of the Report 10

2      Project Background. 12

2.1        Background. 12

2.2        Scope of the Project and Site Description. 12

2.3        Division of the Project Responsibility. 13

2.4        Project Organization and Contact Personnel 14

3      Status of Regulatory Compliance. 18

3.1        Status of Environmental Licensing and Permitting under the Project 18

4      Monitoring Requirements. 28

4.1        Noise Monitoring. 28

4.2        Air Monitoring. 29

4.3        Water Quality Monitoring. 32

5.     Monitoring Results. 37

5.1        Noise Monitoring Results. 37

5.2        Air Monitoring Results. 40

5.3        Water quality monitoring Results. 42

5.4        Waste Monitoring Results. 48

6.     Compliance Audit. 53

6.1        Noise Monitoring. 53

6.2        Air Monitoring. 54

6.3        Water Quality Monitoring. 55

6.4        Review of the Reasons for and the Implications of Non-compliance. 57

6.5        Summary of action taken in the event of and follow-up on non-compliance. 57

7.     Cumulative Construction Impact due to the Concurrent Projects. 58

8.     Environmental Site Audit. 59

9. Complaints, Notification of Summons and Prosecution. 61

10.    Conclusion. 62


lIST OF TABLES

 

Table I        Summary of Water Quality Monitoring Exceedances in Reporting Month

Table II       Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 2.1    Schedule 2 Designated Projects under this Project

Table 2.2     Details of Individual Contracts under the Project

Table 2.3     Contact Details of Key Personnel

Table 3.1     Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.3     Summary of submission status under FEP-02/356/2009 Condition

Table 3.4     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.5     Summary of submission status under FEP-03/356/2009 Condition

Table 3.6     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.7     Summary of submission status under FEP-04/356/2009 Condition

Table 3.8     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.9     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Table 3.10   Summary of submission status under EP-356/2009 & FEP-06/356/2009 Condition

Table 3.11   Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08

Table 3.12   Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition

Table 4.1     Noise Monitoring Station

Table 4.2     Air Monitoring Station

Table 4.3    Marine Water Quality Stations for Water Quality Monitoring

Table 4.4     Marine Water Quality Monitoring Frequency and Parameters

Table 4.5    Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 5.1    Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02

Table 5.2    Noise Monitoring Station for Contract no. HY/2009/15

Table 5.3    Noise Monitoring Station for Contract no. HY/2009/19

Table 5.4    Noise Monitoring Station for Contract no. HY/2010/08

Table 5.5    Air Monitoring Station for Contract no. HK/2009/01

Table 5.6    Air Monitoring Station for Contract no. HK/2009/02

Table 5.7    Air Monitoring Station for Contract no. HY/2009/15

Table 5.8    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.9     Air Monitoring Stations for Contract no. HK/2012/08

Table 5.10   Air Monitoring Stations for Contract no. HY/2010/08

Table 5.11   Water quality monitoringStations for contracts with respect to remaining DP3 work areas after the completion of DP5 & DP6 in 2012 and intake diversion in 2013

Table 5.12   Water quality monitoringStations for Contract no. HK/2009/01

Table 5.13   Water quality monitoringStations for Contract no. HK/2009/02

Table 5.14   Water quality monitoringStations for Contract no. HK/2012/08

Table 5.15   Water quality monitoringStations for Contract no. HY/2009/15

Table 5.16   Enhanced Dissolved Oxygen Monitoring Stations for Contract no. HY/2009/15

Table 5.17   Water quality monitoring Station for Contract no. HY/2010/08

Table 5.18   Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2010/08

Table 5.19   Details of Waste Disposal for Contract no. HK/2009/01

Table 5.20   Details of Waste Disposal for Contract no. HK/2009/02

Table 5.21   Details of Waste Disposal for Contract no. HY/2009/15

Table 5.22   Details of Waste Disposal for Contract no. HY/2009/19

Table 5.23  Details of Waste Disposal for Contract no. HK/2012/08

Table 5.24  Details of Waste Disposal for Contract no. HY/2010/08

Table 8.2    Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2012/08

Table 8.6     Summary of Environmental Inspections for Contract no. HY/2010/08

Table 9.1     Cumulative Statistics on Complaints

Table 9.2     Cumulative Statistics on Successful Prosecutions

Table 10.1   Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

 

 

lIST OF FIGUREs

 

Figure 2.1     Project Layout

Figure 2.2     Project Organization Chart

Figure 4.1    Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Water Quality Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Summary for Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1  Construction Programme of Individual Contracts


EXECUTIVE SUMMARY

       i.        This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V June 2017 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009. This report presents the environmental monitoring findings and information recorded during the period of 27th May 2017 to 26th June 2017. The cut-off date of reporting is at 26th of each reporting month.

 

Construction Activities for the Reported Period

 

      ii.        During this reporting period, the major work activities for Contract no. HK/2009/01 included:

¡P          Nil

 

     iii.        During this reporting period, the major work activities for Contract no. HK/2009/02 included:

Ÿ   Nil

 

     iv.        During this reporting period, the major work activities for Contract no. HY/2009/15 included:

¡P          Nil

 

      v.        During this reporting period, the major work activities for Contract no. HY/2009/19 included:

Ÿ   Nil

 

     vi.        During this reporting period, the major work activities for Contract no. HK/2012/08 included:

¡P          Construction of Box 1 unit

 

    vii.        During this reporting period, the major work activities for Contract no. HY/2010/08.

¡P          Diversion pipe maintenance

¡P          Diaphragm Wall Removal Works

¡P          Removal of reclamation at TS3E and TS3W

 

Noise Monitoring

   viii.        With respect to the shift in major construction site portions at Wan Chai North, the noise monitoring station M1a ¡V Harbour Sports Centre was finely adjusted from East of Harbour Road Sports Centre to West of Harbour Road Sports Centre on 21 June 2016.

     ix.        With respect to the demolition of Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a ¡V Harbour Road Sports Centre were finely adjusted on 16 and 25 May 2017 and thereafter to the Footbridge for Harbour Road Sports for noise monitoring.

      x.        School examination was scheduled to be taken place at Henrietta Secondary School from 7 June 2017 to 9 June 2017, 12 June 2017 to 16 June 2017 and 19 June 2017 to 21 June 2017, the limit level of noise monitoring at station M6 was adjusted to 65dB(A) during examination period accordingly.

    xi.        Five limit level exceedances were recorded at M1a ¡V Footbridge for Ex-Harbor Road Sports Centre on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting month. The exceedances were concluded as non-Project related.

    xii.        Three limit level exceedances were recorded at M6 - HK Baptist Church Henrietta Secondary School on 08, 16 and 19 June 2017 in the reporting month. The exceedances were concluded as non-Project related.

   xiii.        Noise monitoring during daytime and restricted hour were conducted at the stations M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting month.

 

Air Quality Monitoring

   xiv.        Due to electricity supply interruption, the TSP monitoring in the reporting month were rescheduled as follow:

24 TSP monitoring at CMA1b was rescheduled from 8 and 14 June 2017 to 14 and 15 June 2017 respectively.

24 TSP monitoring at CMA5b was rescheduled from 14 and 26 June 2017 to 15 and 28 June 2017 respectively.

24 TSP monitoring at CMA6a was rescheduled from 20 June 2017 to 22 June 2017.

  xv.        One limit level exceedance was recorded at CMA1b ¡V Oil Street Site Office was recorded on 03 June 2017 in the reporting month. The exceedance was concluded as non-Project related.

   xvi.        One limit level exceedance was recorded at CMA5b ¡V Pedestrian Plaza was recorded on 03 June 2017 in the reporting month. The exceedance was concluded as non-Project related.

  xvii.        With respect to the proposed demolition of the Oil Street Site Office, the respective air quality monitoring station CMA1b ¡V Oil Street Site Office was finely adjusted from the Oil Street Site Office to Harbour Grand Hotel Boundary Wall from 05 June 2017 onwards.

 xviii.        With respect to the proposed demolition of eastern podium of Oil Street Site Office, the respective air quality monitoring station CMA1b ¡V Oil Street Site Office was finely adjusted from East podium of the Oil Street Site Office to the West podium of the Oil Street Site Office on 21 December 2016.

   xix.        1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b ¡V Oil Street Site Office; CMA2a ¡V Causeway Bay Community Center; CMA3a ¡V CWB PRE Site Office Area; CMA4a ¡V Society for the Prevention of Cruelty to Animals; CMA5b ¡V Pedestrian Plaza; CMA6a ¡V WDII PRE Site Office in the reporting month.

 

Water Quality Monitoring

    xx.        Due to the malfunctioning of the pump system for water cooling intake for Windsor House Station at water quality monitoring station C7, the water quality monitoring at respective station C7 on 26 June 2017 during flood tide was cancelled. The water quality monitoring at C7 was subsequently resumed on 26 June 2017 during ebb tide upon resumption of fresh water supply to the aforesaid cooling water intake location via the water holding tank.

   xxi.        Due to the hoisting of Strong Wind Signal No. 3, the scheduled water quality monitoring event on 12 June 2017 during ebb tide was cancelled.

  xxii.        Water quality monitoring station C7 and Enhance DO monitoring station C6 shall be associated with Contract HY/2010/08, upon confirmation of marine construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.

 xxiii.        Referring to CWB RSS confirmation on the completion of marine construction activities within the Ex-PCWA area and the completion of the post construction water quality monitoring, the respective Enhance DO Monitoring within Ex-PCWA for monitoring station Ex-PCWA SE and Ex-PCWA SW was temporarily suspended since 07 March 2017 ebb tide onwards.

xxiv.        With respect to the reinstatement of the silt screen system for Cooling Water Intakes P7, P8, P9 and WSD Water Intake RW21, the respective water quality monitoring was reverted to the previous monitoring location for Water Quality Monitoring Station RW21-P789 from water quality stations RW21-P789 East (RW21-P789E) and RW21-P789 West (RW21-P789W) from 25 January 2017 onwards.

 xxv.        With respect to the removal of silt screen at WQM station RW21-P789 on 26 November 2016, the respective water quality monitoring at RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.

xxvi.        With respect to the temporarily suspension of marine construction works at WCR3 Area by Contract HK/2009/02, the installed silt screen for intake group (P7, P8, P9 and WSD21) was removed on 26 November 2016.

xxvii.        As advised by the Contractor of HK/2009/01, all silt screen remains removal works at P1, P3, P4, P5 and C1 water quality monitoring stations were completed on 8 May 2016.

xxviii.        With respect to the marine works undertaken at WCR3 by Contract HK/2009/02, the respective water quality monitoring station C1 associated with Contract HK/2009/01 was updated as in association with Contract HK/2009/01 and Contract HK/2009/02.

xxix.        With respect to the marine works undertaken at CBTS by Contract HY/2010/08, the respective water quality monitoring station C7 associated with Contract HY/2009/15 was updated as in association with Contract HY/2009/15 and Contract HY/2010/08.

 xxx.        With respect to the marine works undertaken at HKCEC2 by Contract HK/2012/08, the respective water quality monitoring station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08.

 

Table I    Summary of Water Quality Monitoring Exceedances in Reporting Month

 

Contract no.

Water quality monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/01 & HK/2009/02

C1

0

0

0

0

0

0

0

0

0

0

0

0

HK/2012/08

WSD19

0

0

0

0

0

0

0

0

0

0

0

0

P1

0

0

0

0

0

0

0

0

0

0

0

0

P3

0

0

0

0

0

0

0

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

RW21-P789

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15 & HY/2010/08

C7

0

0

0

2

1

0

0

0

0

2

1

0

Total

0

0

0

2

1

0

0

0

0

2

1

0

Remarks: -     The cessation of seawater intake operation for C6 was confirmed on 17 May 2011 and the water quality monitoring at C6 was then terminated since 17 May 2011.

          -  4-week post construction water quality monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 2012 onwards.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-       C8 & C9 were temporary suspended since 4 March 2013.

-   WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

-      C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 22 Apr 2013

-      P1, P3, P4 and P5 were commenced since 24 Apr 2013

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 Jul 2013.

-       WSD21 water quality monitoring station was temporarily suspended since 12 Mar 2014

-       WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 Sep 2014 flood tide.

-     The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.

-      The water quality monitoring station RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.

-       The water quality monitoring was reverted to previous monitoring station RW21-P789 from PW21-P789E and RW21-P789W from 25 January 2017 onwards.

 

xxxi.        There were four limit level of turbidity exceedances and two action level of suspended solid exceedance were recorded in this reporting month.

xxxii.        Investigation found that 1 limit level of turbidity exceedance recorded at monitoring station C7 on 23 June 2017 was not related to Project works.

xxxiii.        Investigation found that 3 limit level of turbidity exceedances and 2 action level of suspended solid exceedances recorded at monitoring station C7 on 21 and 26 June 2017 were concluded as related to Project works.

xxxiv.        The details of the recorded exceedances can be referred to the Section 6.3.

 

xxxv.        Enhanced DO monitoring at 3 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table II.

 

Table II   Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

 

 

Water quality monitoring Station

Mid-flood

Mid-ebb

 

Contract no.

DO

DO

 

 

AL

LL

AL

LL

 

HY/2009/15 & HY/2010/08

C6

0

0

0

0

 

Total

0

0

0

0

Remarks:

1.   Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

2.   Enhanced DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from 31 August 2015 with respect to seawall reinstatement works and formation of active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11 May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.

 

xxxvi.        No action or limit level exceedance for enhanced dissolved oxygen monitoring recorded in this reporting month.

 

Complaints, Notifications of Summons and Successful Prosecutions

xxxvii.        There was no environmental complaint received in this reporting month.

 

Site Inspections and Audit

xxxviii.        The Environmental Team (ET) conducted weekly site inspections for Contract nos. HK/2009/01, HK/2009/02, HY/2009/15, HY/2009/19, HK/2012/08 and HY/2010/08 under EP no. EP-356/2009 in the reporting month. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.

 

Future Key Issues

xxxix.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Ÿ   Nil

 

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East

¡P          Nil

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          Nil

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

¡P            Nil

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P          Construction of Box 1 unit

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

¡P          Diversion pipe maintenance

¡P          Diaphragm Wall Removal works

¡P          Removal of reclamation at TS3E and TS3W

1      Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 during the period of 27th May 2017 to 26th June 2017. The cut-off date of reporting is at 26th of each reporting month.

 

1.2          Structure of the Report

 

Section 1        Introduction ¡V details the scope and structure of the report.

 

Section 2        Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5        Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Environmental Site Audit ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10       Conclusion

2      Project Background

2.1          Background

2.1.1.     ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.     The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.     The scope of the Project comprises:

¡P          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

¡P          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

¡P          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

¡P          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

¡P          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

¡P          Construction of the new waterfront promenade, landscape works and the associated utility services

¡P          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1      Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table 2.2.

 

 

 

Table 2.2 Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point Reclamation

DP3

17 March 2010

(Completed)

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HY/2009/17

Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

HY/2009/19

Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2012/08

Wan Chai Development Phase II Central-

Wan Chai Bypass at Wan Chai

West

DP1,DP2, DP3

10 March 2014

HY/2010/08

Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central-Wan Chai Bypass (CWB) ¡V Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

 

Table 2.3 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3328

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Manager

Mr. Simon Liu

9304 8355

2587 1878

Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Wyman Wong

9627 2467

Environmental Officer

Mr. Terry Tsang

6683 9394

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Paul Yu

3658-3085

2827 9996

Quality & Environmental Manager

Mr. C.P. Ho

9191 8856

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Chris Leung

3557 6393

2566 2192

 

Senior Site Manager

Y Huo

3557 6368

Contractor¡¦s Representative

Rex Lau

3557 6405

Environmental Officer

Andy Mak

3557 6347

 

Chun Wo ¡V CRGL ¡V MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

 

Project Manager

Rayland Lee

3758 6788

3757 8901

Site Agent

David Lau

3758 8879

Deputy Site Agent

Andy Chan

9879 4325

Environmental Manager /

Environmental Officer

M.H. Isa

9884 0810

 

 

Construction Manager (Marine)

Wingo Wong

9300 2625

 

Construction Manager (Land)

Ivan Wong

9200 7552

China State-

Build King Joint Venture

Contractor

under Contract

no. HK/2012/08

Project Director

C. N. Lai

9106 5806

2877 1522

Project Manager

Eddie Chung

9189 8118

Site Agent

Keith Tse

9037 1839

Environmental Officer

James Ma

9130 9549

China State

 

Contractor

under Contract

no. HY/2010/08

Project Director

Chris Leung

9210 7116

2566 8061

 

 

 

Project Manager

Chan Ying Lun

3418 3001

 

 

Site Agent

Thomas Lui

3557 6452

 

 

Environmental Officer

Gabriel Wong

35576466

 

 

Environmental Supervisor

Desmond Ho Tsz Ho

3557 6466

Ramboll Environ Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

2.4.3.     For Contract no. HK/2009/01, the principal work activities in this reporting month included:

Ÿ   Nil

 

2.4.4.     For Contract no. HK/2009/02, the principal work activities in this reporting month included:

Ÿ   Nil

 

2.4.5.     For Contract no. HY/2009/15, the principal work activities in this reporting month included:

¡P          Nil

 

2.4.6.     For Contract no. HY/2009/19, the principal work activity in this reporting month included:

Ÿ   Nil

 

2.4.7.     For Contract no. HK/2012/08, the principal work activity in this reporting month included:

¡P          Construction of Box 1 unit

 

2.4.8.     For Contract no. HY/2010/08, no principal work activities this reporting month.

¡P          Diversion pipe maintenance

¡P          Diaphragm Wall Removal Works

¡P          Removal of reclamation at TS3E and TS3W

 

 

 

 

2.4.9.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Ÿ   Nil

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East

¡P          Nil

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          Nil

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ   Nil

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P          Construction of Box 1 unit

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

¡P          Diversion pipe maintenance

¡P          Diaphragm Wall Removal Works

¡P          Removal of reclamation at TS3E and TS3W

3      Status of Regulatory Compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Superseded

Environmental Permit

EP-364/2009/C

11 Jul 2014

Superseded

Environmental Permit

EP-364/2009/D

24 Nov 2016

Superseded

Environmental Permit

EP-364/2009/E

22 Dec 2016

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Surrendered

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/B

20 Sep 2012

Surrendered

Further Environmental Permit

FEP-07/364/2009/D

24 Nov 2015

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 Jun 2012

Surrendered

Further Environmental Permit

FEP-06/356/2009

5 Mar 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

Further Environmental Permit

FEP-11/364/2009/B

2 May 2014

Superseded

Further Environmental Permit

FEP-08/356/2009

1 Aug 2016

Valid

Further Environmental Permit

FEP-11/364/2009/E

22 Dec 2016

Valid

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HK/2010/06 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line under FEP-05/356/2009

3.1.3.     The construction works were completed and the FEP-05/356/2009 was surrendered by the Contractor on 3 October 2014.

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

3.1.4.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.2 and Table 3.3.

Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS1241-16

12 Dec 2016

15 Dec 2016 to 6 Jun 2017

Expired

GW-RS1240-16

12 Dec 2016

13 Dec 2016 to 6 Jun 2017

Expired

 

GW-RS1233-16

12 Dec 2016

14 Dec 2016 to 6 Jun 2017

Expired

 

GW-RS1234-16

12 Dec 2016

20 Dec 2016 to 19 Jun 2017

Expired

Discharge Licence

WT00024952-2016

6 Jul 2016

31 Jul 2021

Valid

 

WT00024844-2016

29 Jun 2016

31 Mar 2020

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.3 Summary of submission status under FEP-02/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

13 Apr 2010

Condition 2.7

Works Schedule and Location Plan

8 Apr 2010

Condition 2.8

Silt Curtain Deployment Plan (Rev. 5)

24 Aug 2012

Silt Curtain Deployment Plan (Rev. 4)

12 July 2012

Silt Curtain Deployment Plan (Rev. 3)

27 June 2012              

Silt Curtain Deployment Plan

19 Apr 2010

Condition 2.9

Silt Screen Deployment Plan (Rev. 9)

5 Nov 2015

Silt Screen Deployment Plan (Rev. 8)

7 Sep 2015

Silt Screen Deployment Plan (Rev. 7)

21 Nov 2014

Silt Screen Deployment Plan (Rev. 6)

20 Aug 2014

Silt Screen Deployment Plan (Rev.5)

24 Jul 2013

Silt Screen Deployment Plan (Rev.4)

15 Nov 2012

Silt Screen Deployment Plan

19 Apr 2010

Conditions 2.8 and 2.9

Supplementary Document on Silt Curtain and Silt Screen Deployment Plan

19 Jul 2010

Report on Field Testing for Silt Curtain

26 Aug 2010

Report on Field Testing for Silt Curtain (Rev. A)

15 Nov 2010

Condition 2.12(d)

Alternative Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains

15 Apr 2011

Condition 2.17

Noise Management Plan

23 Apr 2010

Condition 2.18

Landscape Plan (Erection of Decorative Screen Hoarding along Construction Site around Hong Kong Exhibition and Convention Centre)

15 May 2010

 

Landscape Plan (Night-time Lighting)

22 Oct 2010

 

Landscape Plan (Rev. B)

15 Nov 2010

Condition 1.12

Notification of Commencement Date

20 Jun 2011

Condition 2.6 to 2.8

Management Organization, Works Schedule and Location Plan

18 May 2011

Condition 2.9

Silt Screen Deployment Plan

10 Jun 2011

Condition 2.18

Landscape Plan

31 Oct 2013

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

3.1.5.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table 3.4 and Table 3.5.

Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

 

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

 

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0289-17

31 Mar 2017

2 Apr 2017 to 2 Jul 2017

Valid

GW-RS0314-17

7 Apr 2017

11 Apr 2017 to 4 Oct 2017

Valid

GW-RS0338-17

13 Apr 2017

28 May 2017 to 27 Aug 2017

Valid

GW-RS0348-17

18 Apr 2017

25 Apr 2017 to 24 Oct 2017

Valid

 

GW-RS0527-17

16 Jun 2017

17 Jun 2017 to 20 Sep 2017

Valid

 

GW-RS0535-17

16 Jun 2017

17 Jun 2017 to 20 Sep 2017

Valid

Discharge Licence

WT00022295-2015

12 Aug 2015

31 July 2020

Valid

 

WT00025276-2016

19 Sep 2016

31 July 2021

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance (Marine)

7011496

6 Oct 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

Marine Dumping Permit (Dredged Sediment Requiring Type 1 ¡V Open Sea Disposal)

EP/MD/17-191

16 May 2017

18 May 2017 to 17 Nov 2017

Valid

 

Table 3.5 Summary of submission status under FEP-03/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 1.12

Commencement Date of Construction of Marine Works

8 April 2010

Condition 2.6

Management Organization of Main Construction Companies

10 April 2010

Condition 2.7

Works Schedule and Location Plans

8 April 2010

Condition 2.8

Silt Curtain Deployment Plan (Revision A)

20 April 2010

Silt Curtain Deployment Plan (Revision B)

25 May 2010

Silt Curtain Deployment Plan (Revision C)

14 Jun 2010

Silt Curtain Deployment Plan (Revision H)

15 Feb 2011

Silt Curtain Deployment Plan (Revision I)

17 Nov 2011

Silt Curtain Deployment Plan (Revision J)

15 Feb 2012

Silt Curtain Deployment Plan (Revision K)

3 May 2012

Silt Curtain Deployment Plan (Revision L)

25 Oct 2012

Silt Curtain Deployment Plan (Revision M)

30 Nov 2012

 Condition 2.9

Silt Screen Deployment Plan

21 April 2010

Supplementary Information for Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho

5 Oct 2010

Silt Screen Deployment Plan (Revision B)

15 Feb 2012

Silt Screen Deployment Plan (Revision C)

3 May 2012

Silt Screen Deployment Plan (Revision D)

10 Dec 2012

 

Silt Screen Deployment Plan (Revision E)

6 May 2013

 

Silt Screen Deployment Plan (Revision F)

23 Nov 2016

Condition 2.17

Noise Management Plan

6 May 2010

Condition 2.18

Landscape Plan (Decorative Screen Hoarding)

11 May 2010

Landscape Plan (Control of Night Time Lighting)

2 June 2010

Landscape Plan (Combined Version)

20 July 2011

Landscape Plan (Combined Version)

5 Aug 2011

-----

Acknowledge of Submission

22 Aug 2011

 

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

3.1.6.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HY/2009/15 under FEP-04/356/2009 are shown in Table 3.6 and Table 3.7.

 

Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

N/A

Valid

 

 

Table 3.7 Summary of submission status under FEP-04/356/2009 Condition

 

FEP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

30 Sep 2010

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule and Location Plans

27 Oct 2010

 

Amendment for Works Schedule and Location Plans

12 Nov 2010

Condition 2.8

Silt Curtain Deployment Plan

30 Nov 2010

 

Amendment for Silt Curtain Deployment Plan

24 Feb 2011

Amendment for Silt Curtain Deployment Plan

11 May 2011

Amendment for Silt Curtain Deployment Plan

11 Sep 2012

Amendment for Silt Curtain Deployment Plan

30 Oct 2012

Condition 2.9

Silt Screen Deployment Plan

19 Oct 2010

Amendment for Silt Screen Deployment Plan

18 Feb 2011

Amendment for Silt Screen Deployment Plan

15 Jun 2011

Condition 2.18

Proposal for the Removal of Odorous Sediment and Slime

13 Jan 2011

Amendment for Proposal for the Removal of Odorous Sediment and Slime

8 Mar 2011

 

Amendment for Proposal for the Removal of Odorous Sediment and Slime

2 Aug 2011

Condition 2.21

Landscape Plan

18 Feb 2011

Condition 2.23

Noise Management Plan

20 Oct 2010

Amendment for Noise Management Plan

27 Jan 2011

 

 

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

3.1.7.     Summary of the current status on licences and/or permits on environmental protection pertinent for contract no. HY/2009/19 is shown in Table 3.8

 

Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permit / Licence / Notification / Approval

Reference No.

Issued Date

Valid Period / Expiry date

Status

Further Environmental Permit

FEP-07/364/2009/D

24 Nov 2015

Granted

Valid

Notification of Works Under APCO

326160

24 Jan 2011

Notified

Valid

Construction Noise Permit (CNP) (For Portion Vi Marine)

GW-RS1251-16

7 Dec 2016

18 Dec 2016 to 17 Jun 2017

Expired

C&D Waste Disposal

7012306

10 Feb 2011

Registered

-

Vessel Disposal

7013285

21 July 2011

Registered

-

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

Registered

-

 

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

3.1.8.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2012/08 under FEP-08/356/2009 are shown in Table 3.9 and Table 3.10.

Table 3.9 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-06/356/2009

5 Mar 2013

N/A

Valid

 

FEP-08/356/2009

1 Aug 2016

N/A

Valid

Notification of Works Under APCO

355439

4 Feb 2013

N/A

Valid

Registration as a Chemical Waste Producer

5213-134-C3790-01

30 Jun 2016

N/A

Valid

Billing Account under Waste Disposal Ordinance

7016883

18 Feb 2013

18 Jul 2017

Valid

Water Discharge Licence

WT00020594-2014

22 Dec 2014

31 Jan 2019

Valid

Construction Noise Permit

GW-RS1335-16

29 Dec 2016

13 Jan 2017 to 12 Jul 2017

Valid

 

GW-RS1336-16

29 Dec 2016

13 Jan 2017 to 12 Jul 2017

Valid

 

GW-RS1349-16

23 Dec 2016

13 Jan 2017 to 12 Jul 2017

Valid

 

GW-RS0098-17

1 Feb 2017

26 Feb 2017 to 25 Aug 2017

Valid

 

GW-RS0385-17

27 Apr 2017

5 May 2017 to 4 Nov 2017

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/17-160

6 Feb 2017

8 Feb 2017 to 30 Jun 2017

Valid

 

 

 

Table 3.10     Summary of submission status under EP-356/2009 and FEP-06/356/2009 Condition

FEP Condition

Submission

Date of Submission

Condition 2.8

Silt Curtain Deployment Plan (Rev. 3)

Submitted on 25 Nov 2013 was returned to CSLJV by EPD.

Condition 2.9

Silt Screen Deployment Plan (Rev. 2)

Generally in order as commented by EPD on 19 Sep 2013

Condition 2.23

Noise Management Plan (Rev. 2)

Generally in order as commented by EPD on 15 Aug 2013

Condition 2.24

Landscape Plan (Rev. 3)

Generally in order as commented by EPD on 31 Oct 2013

 

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

3.1.9.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HY/2010/08 under FEP-07/356/2009 are shown in Table 3.11 and Table 3.12.

 

Table 3.11     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/356/2009

26 Jul 2013

NA

Valid

 

FEP-10/364/2009/B

26 Jul 2013

NA

Valid

Notification of Works Under APCO

357176

2 Apr 2013

NIL

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-44

27 Mar 2013

NIL

Valid

Billing Account under Waste Disposal Ordinance

7017170

27 Mar 2013

NIL

Valid

Billing Account under Waste Disposal Ordinance (Dumping by Vessel)

7020947

22 Dec 2014

NIL

Valid.

Water Discharge Licence

WT00020753-2015

3 Feb 2015

28 Feb 2017

Valid

Construction Noise Permit

GW-RS0289-17

31 Mar 2017

2 Apr 2017 to 2 Jul 2017

Valid

 

GW-RS0347-17

27 Apr 2017

27 Apr 2017 to 18 Oct 2017

Valid

 

Table 3.12     Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition

FEP Condition

Submission

Date of Submission

Condition 2.8

Silt Curtain Deployment Plan (rev03)

24 Dec 2014

Condition 2.9

Silt Screen Deployment Plan (rev02)

18 Feb 2015

Condition 2.23

Noise Management Plan (rev02)

25 Mar 2014

Condition 2.24

Landscape Plant (rev04)

23 Sep 2014

4         Monitoring Requirements

4.1          Noise Monitoring

Noise Monitoring Stations

4.1.1.     The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1 Noise Monitoring Station

Station

Description

M1a

Footbridge for Ex-Harbour Road Sports Centre*

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

Remarks*: With respect to the demolition of Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a ¡V Harbour Road Sports Centre were finely adjusted on 16 and 25 May 2017 and thereafter to the Footbridge for Harbour Road Sports for noise monitoring

Noise Monitoring Parameters, Frequency and Duration

4.1.2.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.3.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

¡P          One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.4.     If construction works are extended to include works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.5.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.6.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

 

4.2          Air Monitoring

Air Quality Monitoring Stations

4.2.1.     The air monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2 Air Monitoring Station

Station ID

Monitoring Location

Description

CMA1b

Harbour Grand Hotel Boundary Wall**

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5b

Pedestrian Plaza***

Wan Chai

CMA6a

WDII PRE Site Office *

Wan Chai

Remarks*: As per the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB site office at Wanchai Waterfront Promenade was renamed as remark.

Remarks**: The location ID of monitoring station CMA1b was updated as ¡§Harbour Grand Hotel Boundary Wall¡¨ from 05 June 2017 onwards.

Remarks***: The station ID and monitoring location was updated in December 2014 with respect to monitoring station relocation.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P          0.6 ¡V 1.7 m3 per minute adjustable flow range;

¡P          equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P          installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P          capable of providing a minimum exposed area of 406 cm2;

¡P          flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P          equipped with a shelter to protect the filter and sampler;

¡P          incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P          equipped with a flow recorder for continuous monitoring;

¡P          provided with a peaked roof inlet;

¡P          incorporated with a manometer;

¡P          able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P          easily changeable filter; and

¡P          capable of operating continuously for a 24-hour period.

 

4.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

 

Laboratory Measurement / Analysis

4.2.7.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.     An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.

4.2.9.     Filter paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.10.   After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.11.   All the collected samples shall be kept in a good condition for 6 months before disposal.

impact monitoring for odour patrol

4.2.12.   Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous sediment and slime at the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at bi-weekly intervals during July, August and September by a qualified person of the ET who shall:

¡P          be at least 16 years of age;

¡P          be free from any respiratory illnesses; and

¡P          not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min

¡P          before and during odour patrol

4.2.13.   Odour patrol shall be conducted by independent trained personnel / competent persons patrolling and sniffing around the shore as shown in Figure 4.1 to detect any odour at the concerned hours (afternoon is preferred for higher daily temperature).

4.2.14.   The qualified person will use the nose (olfactory sensor) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance will be identified.

4.2.15.   The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:

¡P          0 ¡V Not detected. No odour perceived or an odour so weak that it cannot be easily characterized or described;

¡P          1 ¡V Slight Identifiable odour, and slight chance to have odour nuisance;

¡P          2 ¡V Moderate Identifiable odour, and moderate chance to have odour nuisance;

¡P          3 ¡V Strong Identifiable, likely to have odour nuisance;

¡P          4 ¡V Extreme Severe odour, and unacceptable odour level.

 

4.2.16.   The findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location will be recorded. In addition, some relevant meteorological and tidal data such as daily average temperature, and daily average humidity, on that surveyed day will be obtained from the Hong Kong Observatory Station for reference. The Action and Limit levels for odour patrol are shown in Appendix 4.1.

4.2.17.   The qualified odour patrol member has individual n-butanol thresholds complied with the requirement of European Standard Method of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80 ppb.

4.3          Water Quality Monitoring

4.3.1.     The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase. Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

4.3.2.     The updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet season (April ¡V September) will be effected and applied to the water quality monitoring data from 30 April 2011.

Water Quality Monitoring Stations

4.3.3.     Water quality monitoring was undertaken at 8 monitoring stations for WSD salt water intakes and cooling water intakes along the seafront of the Victoria Harbour in the reporting month. The proposed water quality monitoring stations of the Project are shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3      Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD19

Sheung Wan

833415.0

816771.0

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C7

Windsor House

837193.7

816150.0

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

Cooling Water Intake / WSD Salt Water Intake

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt water intake / China Resources Building

836268.0

816020.0

Remarks: -     The cessation of seawater intake operation for C6 was confirmed on 17 May 2011 and the water quality monitoring at C6 was then terminated since 17 May 2011.

          -  4-week post construction water quality monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 2012 onwards.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-       C8 & C9 were temporary suspended since 4 March 2013.

-   WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

-      C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 22 Apr 2013

-      P1, P3, P4 and P5 were commenced since 24 Apr 2013

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 Jul 2013.

-       WSD21 water quality monitoring station was temporarily suspended since 12 Mar 2014

-       WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 Sep 2014 flood tide.

-      The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.

-      The water quality monitoring station RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.

-       The water quality monitoring was reverted to previous monitoring station RW21-P789 from PW21-P789E and RW21-P789W from 25 January 2017 onwards.

 

Water Quality Parameters

4.3.4.     Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory.

4.3.5.     In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

 

Sampling Procedures and Monitoring Equipment

4.3.6.     The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased. Table 4.4 shows the proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water sampling should be carried out in each sampling event. For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

Table 4.4 Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.     For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.     Turbidity should be measured in situ whereas SS should be determined by laboratory.

 

 

 

Dissolved Oxygen and Temperature Measuring Equipment

4.3.7.     The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

¡P          a dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation

¡P          a temperature of 0-45 degree Celsius

4.3.8.     It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

4.3.9.     Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

4.3.10.   The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Sampler

4.3.11.   A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

Sample Container and Storage

4.3.12.   Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.

Water Depth Detector

4.3.13.   A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.

Salinity

4.3.14.   A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.

Monitoring Position Equipment

4.3.15.   A hand-held or boat-fixed type digital Global Positioning System (GPS) with waypoint bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-situ Instruments

4.3.16.   All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

4.3.17.   For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.

4.3.18.   Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

4.3.19.   Current calibration certificates of equipments are presented in Appendix 4.2.

Laboratory Measurement / Analysis

4.3.20.   Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.

Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo

Working Area and the Causeway Bay Typhoon Shelter

4.3.21.   The enhanced water quality monitoring and audit programme is to avoid aggravation of odour nuisance from seawater arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.

4.3.22.   Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The proposed water quality monitoring stations of the Project are shown in Table 4.5 and Figure 4.1.

Table 4.5      Marine Water Quality Stations for Enhanced Water Quality Monitoring

Station

Location

C6

Excelsior Hotel

C7

Windsor House

Ex-WPCWA-SW

South-western of the ex-Wan Chai Public Cargo Working Area

Ex-WPCWA-SE

South-eastern of the ex-Wan Chai Public Cargo Working Area

 

 

Remarks:

1.   Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

2.   Enhanced DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from 31 August 2015 with respect to seawall reinstatement works and formation of active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11 May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.

 

4.3.23.   The monitoring of dissolved oxygen are to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).

 

Daily SS Monitoring and 24 hours Turbidity Monitoring System

4.3.24.   During dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.

4.3.25.   The 24 hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be established by setting up a continuous water quality monitoring station in front of the intakes during the dredging activities. The monitoring system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the Action and Limit level determined during the baseline water qualtiy monitoring at the cooling water intake locations.

 

 

Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW

4.3.26.   In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

4.3.27.   With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

4.3.28.   The monitoring of dissolved oxygen are to be carried out once per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).  

5.         Monitoring Results

5.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.     In the reporting month, the concurrent contracts are as follows:

Ÿ  Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Hong Kong Convention and Exhibition Centre; and

Ÿ  Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai East

Ÿ  Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

Ÿ  Contract no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ  Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

Ÿ  Contract no. HY/2010/08 ¡V Central- Wanchai Bypass Tunnel (Slip Road 8 Section)

 

5.0.3.     The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

 

5.1          Noise Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.1.1.     The proposed division of noise monitoring stations are summarized in Table 5.1 below.

Table 5.1 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Station

Description

M1a

Footbridge for Ex-Harbour Road Sports Centre

 

5.1.2.     Five limit level exceedances were recorded at M1a ¡V Footbridge for Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting month.

5.1.3.     No Construction works was conducted under Contract HK/2009/01 around the monitoring station on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting month, non WDII-CWB Projects construction works were observed on 31 May 2017 and 08, 13, 22 and 26 June 2017 during the monitoring period as the major noise contribution. Hence, the exceedances were considered as non-Project related.

5.1.4.     Despite rebar fixing, and formwork fixing works was conducted on 31 May 2017 and 13 and 26 June 2017 under Contract HK/2009/02, and concreting works was conducted on 08 and 22 June 2017 under Contact HK/2009/02, non WDII-CWB Projects construction works was observed on 31 May 2017 and 08, 13, 22 and 26 June 2017 during monitoring period and observed as the major noise contribution. Hence, the exceedances were considered as non-Project related.

5.1.5.     Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.1.6.     The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise monitoring stations are summarized in Table 5.2 below.

Table 5.2      Noise Monitoring Station for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

5.1.7.     No action or limit level exceedance was recorded in this reporting month.

5.1.8.     Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.1.9.     The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3      Noise Monitoring Station for Contract no. HY/2009/19

Station

Description

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

 

 

 

5.1.10.   School examination was scheduled to be taken place at Henrietta Secondary School from 7 June 2017 to 9 June 2017, 12 June 2017 to 16 June 2017 and 19 June 2017 to 21 June 2017, the limit level of noise monitoring at station M6 was adjusted to 65dB(A) during examination period accordingly.

5.1.11.   Three limit level exceedances were recorded at M6 ¡V HK Baptist Church Henrietta Secondary School on 08, 16 and 19 June 2017 in this reporting month.

5.1.12.   Despite lifting works by crane and falsework erection works were conducted on 08 and 19 June 2017 respectively, no construction activity was conducted on 16 June 2017 and traffic noise was observed as the major noise contribution on 08, 16 and 19 June 2017. Hence, the exceedances were considered as non-Project related.

5.1.13.   Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

Contract no. HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)

5.1.14.   The proposed division of noise monitoring stations are summarized in Table 5.4 below.

Table 5.4      Noise Monitoring Station for Contract no. HY/2010/08

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

 

 

 

5.1.15.   No action or limit level exceedance was recorded in this reporting month.

5.1.16.   Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

 

 

 

 

 

 

 

 


5.2          Air Monitoring Results

  

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.2.1       Air monitoring was commenced on 1 April 2011 in response to the commencement of the land-filling work for Contract no. HK/2009/01. The proposed divisions of air monitoring stations are summarized in Table 5.5 below.

Table 5.5      Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5b

Pedestrian Plaza

CMA6a

WDII PRE Site Office

5.2.2       There was one limit level of 1hr TSP monitoring recorded at monitoring station CMA5b on 3 June 2017.

5.2.3       No construction works was undertaken around the monitoring location on 3 June 2017 and no particular observation regarding air quality impact observed during sampling. Nevertheless, non WDII-CWB Project construction activities and traffic was observed opposite to the monitoring station was observed on 3 June 2017. In addition, it was further observed that garden and sweeping works conducted directly at the monitoring station by Pedestrian Plaza management office could potentially contribute to the elevated particulates level in the vicinity of the monitoring equipment. In view of the above, the exceedance was considered to be non-project related and potentially contributed by localized ambient condition and non-construction activity around the monitoring station.

5.2.4       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.  

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.2.5       Air monitoring was commenced in mid-January 2011 for the land-filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations are summarized in Table 5.6 below.

Table 5.6      Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

5.2.6       No action or limit level recorded in this reporting month.

5.2.7       Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.  

 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.2.8       Air monitoring was commenced on 15 March 2011 for the land filling work for Contract no. HY/2009/15. The proposed division of air monitoring stations are summarized in Table 5.7 below.

Table 5.7      Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

5.2.9       No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.2.10    The proposed division of air monitoring stations are summarized in Table 5.8 below.

Table 5.8   Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Harbour Grand Hotel Boundary Wall

CMA2a

Causeway Bay Community Centre

5.2.11    There was one limit level of 1hr TSP monitoring recorded at monitoring station CMA1b on 3 June 2017.

5.2.12    No construction works was undertaken around the monitoring location on 3 June 2017 and no particular observation regarding air quality impact observed during sampling and dust mitigation measure including haul road and dusty surface maintained in dampened condition were generally implemented. In view of the above, the exceedance was considered to be non-project related and potentially contributed by localized ambient condition and other environmental factor.

5.2.13    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

 

Contract no. HK/2012/08- Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai West

5.2.14    The proposed division of air monitoring stations are summarized in Table 5.9 below.

Table 5.9   Air Monitoring Stations for Contract no. HK/2012/08

Station

Description

CMA5b

Pedestrian Plaza

5.2.15    There was one limit level of 1hr TSP monitoring recorded at monitoring station CMA5b on 3 June 2017.

5.2.16    Manhole installation was undertaken around the monitoring location on 3 June 2017 and no particular observation regarding air quality impact observed during sampling. Nevertheless, non WDII-CWB Project construction activities and traffic was observed opposite to the monitoring station was observed on 3 June 2017. In addition, it was further observed that garden and sweeping works conducted directly at the monitoring station by Pedestrian Plaza management office could potentially contribute to the elevated particulates level in the vicinity of the monitoring equipment. In view of the above, the exceedance was considered to be non-project related and potentially contributed by localized ambient condition and non-construction activity around the monitoring station.

5.2.17    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

 

Contract no. HY/2010/08- Central-Wanchai Bypass Tunnel (Slip Road 8 Section)

The proposed division of air monitoring stations are summarized in Table 5.10 below.

Table 5.10 Air Monitoring Stations for Contract no. HY/2010/08

Station

Description

CMA3a

CWB PRE Site Office

5.2.18    No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

 

5.3          Water quality monitoring Results

5.3.1.     Due to the malfunctioning of the pump system for water cooling intake for Windsor House Station at water quality monitoring station C7, the water quality monitoring at respective station C7 on 26 June 2017 during flood tide was cancelled. The water quality monitoring at C7 was subsequently resumed on 26 June 2017 during ebb tide upon resumption of fresh water supply to the aforesaid cooling water intake location via the water holding tank.

5.3.2.     Due to the hoisting of Strong Wind Signal No. 3, the scheduled water quality monitoring event on 12 June 2017 during ebb tide was cancelled.

5.3.3.     Water quality monitoring station C7 and Enhance DO monitoring station C6 shall be associated with Contract HY/2010/08, upon confirmation of marine construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.

5.3.4.     Referring to CWB RSS confirmation on the completion of marine construction activities within the Ex-PCWA area and the completion of the post construction water quality monitoring, the respective Enhance DO Monitoring within Ex-PCWA for monitoring station Ex-PCWA SE and Ex-PCWA SW was temporarily suspended since 07 March 2017 ebb tide onwards.

5.3.5.     With respect to the reinstatement of the silt screen system for Cooling Water Intakes P7, P8, P9 and WSD Water Intake RW21, the respective water quality monitoring was reverted to the previous monitoring location for Water Quality Monitoring Station RW21-P789 from water quality stations RW21-P789 East (RW21-P789E) and RW21-P789 West (RW21-P789W) from 25 January 2017 onwards.

5.3.6.     With respect to the temporarily suspension of marine construction works at WCR3 Area by Contract HK/2009/02, the installed silt screen for intake group (P7, P8, P9 and WSD21) was removed on 26 November 2016.

5.3.7.     As advised by the Contractor of HK/2009/01, all silt screen remains removal works at P1, P3, P4, P5 and C1 water quality monitoring stations were completed on 8 May 2016.

5.3.8.     With respect to the marine works undertaken at WCR3 by Contract HK/2009/02, the respective water quality monitoring station C1 associated with Contract HK/2009/01 was updated as in association with Contract HK/2009/01 and Contract HK/2009/02.

5.3.9.     With respect to the marine works undertaken at CBTS by Contract HY/2010/08, the respective water quality monitoring station C7 associated with Contract HY/2009/15 was updated as in association with Contract HY/2009/15 and Contract HY/2010/08.

5.3.10.   With respect to the marine works undertaken at HKCEC2 by Contract HK/2012/08, the respective water quality monitoring station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08.

 

Table 5.11 Water quality Monitoring Stations for contracts with respect to remaining DP3 work areas after the completion of DP5 & DP6 in 2012 and intake diversion in 2013

 

Contract No.

Remaining DP3 and work area(s)

Relevant Water quality monitoring Stations,

Division of WQM w.r.t tentative works commenced / to be commenced

HK/2009/01

WCR3

C11

Apr 2013

HK/2009/02

WCR3, WCR4, TWCR4

RW21-P7892, C11

Apr 2013

HK/2012/08

HKCEC2W, HKCEC2E

WSD19, P13, P33, P43, P53

Aug 2013

HY/2009/15

 

TCBR2, TCBR3, TCBR1W, TPCWAE, TPCWAW

C64, C7, Ex-WPCWA SW, Ex-WPCWA SE (plus enhanced DO monitoring)

Nov 2010

HY/2010/08

TCBR3, TCBR4

C64, C7 (plus enhanced DO monitoring)

Mar 2014

 

Remarks:

1.     The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.

2.     4 intakes (re-provisioned Wanchai WSD intake, Great Eagle Centre, China Resources Centre & Sun Hung Kai Centre constructed adjacent to each other) taken as a single group for silt screen protection and monitoring. Re-provisioned intake reference: P1: HKCEC Phase 1; P3: APA, P4: Shui On; P5: Government Buildings (Wanchai Tower / Revenue Tower / Immigration Tower)

3.     The water quality monitoring stations for WSD19, P1, P3, P4, P5 shall be associated with Contract No. HK/2009/01 prior to their transition to Contract HK/2012/08.

4.     Enhanced DO Monitoring at C6 since the intake abandon in May 2011.

5.     With respect to the removal of silt screen at WQM station RW21-P789 on 26 November 2016, the respective water quality monitoring at RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.3.10    Water quality monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The proposed division of water quality monitoring stations are summarized in Table 5.12 below.

 

Table 5.12    Water quality monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

 

5.3.11    No action or limit level was recorded in this reporting month.

5.3.12    Water quality monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

 

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.3.13  Water quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water quality monitoring stations are summarized in Table 5.13 below.

 

Table 5.13   Water quality Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

Cooling Water Intake / WSD Salt Water Intake

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt water intake / China Resources Building

836268.0

816020.0

5.3.14    No action or limit level exceedance was recorded in this reporting month.

5.3.15    Water quality monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

 

Contract no. HK/2012/08 - Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

5.3.16    Water quality monitoring for Contract no. HK/2012/08 was commenced on 5 March 2013. The proposed division of water quality monitoring stations are summarized in Table 5.14 below.

Table 5.14    Water quality Monitoring Stations for Contract no. HK/2012/08

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD19

Sheung Wan

833415.0

816771.0

Cooling Water Intake

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

 

5.3.17    No action or limit level exceedance was recorded in this reporting month.

5.3.18    Water quality monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.3.19    Due to the commencement of the maintenance dredging on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water quality monitoring stations are summarized in Table 5.15 and Table 5.16 below.

 

Table 5.15    Water quality monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C7

Windsor House

837193.7

816150.0

Remarks:

-       The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water quality monitoring at C6 was then terminated since 17 May 2011.

-       Water quality monitoring station C7 shall be associated with Contract HY/2010/08, upon confirmation of marine construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.

 

 

 

 

Table 5.16 Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

C6

Excelsior Hotel

Remarks:

-       Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

-       Enhance DO monitoring station C6 shall be associated with Contract HY/2010/08, upon confirmation of marine construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.

 

5.3.20    No action or limit level exceedance was recorded in this reporting month.

5.3.21    Water quality monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

 

Contract no. HY/2010/08- Central-Wanchai Bypass Tunnel (Slip Road 8 Section)

5.3.22    The proposed division of water quality monitoring stations are summarized in Table 5.17 and Table 5.18 below:

 

Table 5.17    Water quality monitoring Stations for Contract no. HY/2010/08

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C7

Windsor House

837193.7

816150.0

 

 

 

Table 5.18 Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2010/08

Station Ref.

Location

C6

Excelsior Hotel

Remarks:

1.   Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

5.3.23    There was 2 limit level of turbidity exceedances and 1 action level of suspended solid exceedance recorded at monitoring station C7 on 21 June 2017.

5.3.24    Removal of seawall block opposite to the monitoring location was conducted during the monitoring period on 21 June 2017 and turbid dispersion was observed generated from the works area and affecting the water quality at the concerned Windsor House cooling water intake during monitoring sampling.

5.3.25    As such, it was considered that turbidity and suspended solid exceedances were related to Project works and the Contractor was immediately advised to take immediate action to rectify the defects observed and conduct an remediation plan on checking the water holding tank and silt screen installed at the concerned monitoring location to ensure the water quality of the concerned location would not be adversely affected.

5.3.26    Rectification measures including reinstatement of deployed impermeable barriers and silt curtain, conducting cleaning and inspection of silt screen and silt curtain at the concerned water intake location at implement water flushing at the concerned water intake storage tank were observed implemented by 23 June 2017. Additional monitoring in accordance with the Event and Action Plan was conducted on 22 June 2017 and limit level exceedance of water turbidity was recorded. No further turbidity exceedance was recorded on the subsequent monitoring conducted on 23 June 2017, and no further suspended solid exceedance was recorded on the subsequent monitoring on 23 June 2017.

5.3.27    There was 1 limit level of turbidity exceedance recorded at monitoring station C7 on 23 June 2017.

5.3.28    After checking with the Contractor, despite D-wall excavation at TS3E was conducted on the monitoring date, Contractor mitigation measures such as deployment of impermeable barriers and silt curtain was generally in order, and the installed silt screen at the concerned water intake location was generally in order. No particular observation regarding water quality impact was observed during monitoring sampling period. In view of the above, it is considered that there was no information to suggest the exceedance was related to Project works.

5.3.29    There was 1 limit level of turbidity exceedance and 1 action level of suspended solid recorded at monitoring station C7 on 26 June 2017.

5.3.30    Underwater excavation at TS3E was conducted during the monitoring period on 26 June 2017. Owing to the malfunctioning of seawater pump on 26 June 2017 flood tide, fresh water was directly supplied to the storage holding tank for water supply to Windsor House Intake. Subsequently, during the sampling event on 26 June 2017 during ebb tide, turbidity  and suspended solid exceedances were recorded at the water holding tank and hence it was considered potential contamination within water holding tank with direct freshwater supply by Project works site and affecting the water quality at the concerned Windsor House cooling water intake.

5.3.31    As such, it was considered that the turbidity and suspended solid exceedances were related to Project works and the Contractor was immediately advised to take immediate action to rectify the water quality concerned observed and prepare the remediation plan according to the Event and Action Plan to address the water quality concern. Remedial measures including reflushing the concerned water intake location were implemented on 27 June 2017. Additional monitoring in accordance with the Event and Action Plan was conducted on 27 June 2017 and no further turbidity exceedance was recorded. No further suspended solid exceedance was recorded on the subsequent monitoring on 28 June 2017.

5.3.32    Water quality monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

 


5.4      Waste Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.4.1.     No inert C&D waste and non- inert C&D waste disposed in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19     Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

62116.405

TKO137, TM38

Inert C&D materials recycled, m3

NIL

5856.5

N/A

Non-inert C&D materials disposed, m3

NIL

1673.69

SENT Landfill

Non-inert C&D materials recycled, kg

NIL

203993

N/A

Chemical waste disposed, kg

NIL

10250

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

NIL

(Bulk Volume)

97428.2

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

NIL

(Bulk Volume)

52250

(Bulk Volume)

East of Cha Chau

Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers

NIL

 (Bulk Volume)

6773

(Bulk Volume)

East of Cha Chau

     

5.4.2.     There were no marine sediment Type 1- Open Sea Disposal and no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in this reporting month.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East

5.4.3.     No inert C&D waste and Non-inert C&D waste disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.

 

Table 5.20     Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

276075.1

TKO137 / TM 38

Inert C&D materials recycled, m3

NIL

18161

N/A

Non-inert C&D materials disposed, m3

NIL

1515.103

SENT Landfill

Non-inert C&D materials recycled, m3

N/A

N/A

N/A

Chemical waste disposed, kg

NIL

13860

SENT Landfill

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

NIL

240222

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

NIL

146445

(Bulk volume)

East of Sha Chau

5.4.4.     There were no marine sediment Type 1 ¡V Open Sea Disposal and no Type 1 Open Sea Disposal (Dedicate Sties) & Type 2 ¡V Confined Marine Disposal disposed in this reporting month.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.4.5.     No Inert and non-inert C&D material was recycled in this reporting month. Details of the waste flow table are summarized in Table 5.21

Table 5.21     Details of Waste Disposal for Contract no. HY/2009/15

 

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Remarks

Inert C&D materials disposed, m3

NIL

141579.2

Tuen Mun Area 38

NIL

NIL

65216

TKO137 FB

NIL

Inert C&D materials recycled, m3

NIL

8127.21

HY/2010/08

NIL

NIL

304

Ex-PCWA

NIL

NIL

111.9

TS4

NIL

Non-inert C&D materials disposed, m3

NIL

252.2

SENT Landfill

NIL

Non-inert C&D materials recycled, kg

NIL

299361.5

N/A

NIL

Chemical waste disposed, kg

NIL

8,200

N/A

NIL

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

NIL

(Bulk Volume)

156909

(Bulk Volume)

Cheung Chau South

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

NIL

(Bulk Volume)

327746

(Bulk Volume)

East of Sha Chau / South of the Brothers

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers) m3

NIL

(Bulk Volume)

12640

(Bulk Volume)

East of Sha Chau / South of the Brothers

Dredging from TCBR1W / Maintenance dredging

Marine Sediment (Type 2 ¡V Confined Marine Disposal), m3

NIL

9350

(Bulk Volume)

East of Sha Chau

Dredging from Eastern Breakwater of CBTS

Marine Sediment (Type 1 ¡V Open Sea Disposal) , m3

NIL

(Bulk Volume)

600

(Bulk Volume)

East Sha Chau / South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 2¡V Confined Marine Disposal) , m3

NIL

(Bulk Volume)

14,780

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynehetic Containers) , m3

NIL

(Bulk Volume)

2,760

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

 

5.4.6.     There was no Type 1 Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal and Type 1 Open Sea Disposal disposed in this reporting month.

 

 

 

 

Contract no. HY/2009/19 ¡VCentral- WanChai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.4.7.     No inert C&D waste and non-inert C&D waste disposed in this reporting month. Details of the waste flow table are summarized in Table 5.22.

 

Table 5.22 Details of Waste Disposal for Contract no. HY/2009/19

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

355921.04

TM38

Inert C&D materials recycled, m3

NIL

59367

N/A

Non-inert C&D materials disposed, m3

NIL

1068.6

N/A

Non-inert C&D materials recycled, kg

NIL

333.14

N/A

Chemical waste disposed, L

NIL

2.12

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

NIL

162

South Cheung Chau

Marine Sediment (Type 2 ¡V Confined Marine Disposal) , m3

NIL

681

East Sha Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

NIL

4976.00

East Sha Chau

 

5.4.8.     There was no marine sediment Type1- Open Sea Disposal and there was no Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in this reporting month.

 

Contract no. HK/2012/08 ¡VWan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

5.4.9.     There was no Inert C&D waste disposed and no non-inert C&D waste disposed in this reporting month. Details of the waste flow table are summarized in Table 5.23.

 

Table 5.23 Details of Waste Disposal for Contract no. HK/2012/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3 *

NIL

4131

TM38

 

NIL

273

TKO137

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

NIL

315

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

NIL

(Bulk volume)

31759

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

NIL

(Bulk volume)

108542

(Bulk volume)

South of The Brothers (from 27 Aug 2013 onwards)

5.4.10.   There was no Marine Sediment Type 1 ¡V Open Sea Disposal (Delicate Sites) & Type 2 ¡V Confined Marine Disposal and Marine Sediment Type 1 ¡V Open Sea Disposal disposed in this reporting month.

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

5.4.11.   Inert C&D waste was disposed in this reporting month, while no non-inert C&D waste disposed in this reporting month. Details of the waste flow table are summarized in Table 5.24

       Table 5.24 Details of Waste Disposal for Contract no. HY/2010/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

9296.4

 

NIL

53703.0

 

19739.4

TM38

 

TKO137

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

NIL

NIL

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal)

NIL

62559.4

South Cheung Chau / Brothers Island *

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

NIL

28309.2

Brothers Island

Marine Sediment (Type 3 ¡V Special Treatment)

NIL

7780

Brothers Island

5.4.12.   There were no Type 1 ¡V Open Sea Disposal and no Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in this reporting month, and no Type 3- Special Treatment disposed in this reporting month.

6.         Compliance Audit

6.0.1.     The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 6.1.

 

6.1          Noise Monitoring

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

6.1.1       Five limit level exceedances were recorded at M1a ¡V Footbridge for Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting month.

6.1.2       No Construction works was conducted under Contract HK/2009/01 around the monitoring station on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting month, non WDII-CWB Projects construction works were observed on 31 May 2017 and 08, 13, 22 and 26 June 2017 during the monitoring period as the major noise contribution. Hence, the exceedances were considered as non-Project related.

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East 

6.1.3       Five limit level exceedances were recorded at M1a ¡V Footbridge for Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting month.

6.1.4       Despite rebar fixing, and formwork fixing works was conducted on 31 May 2017 and 13 and 26 June 2017 under Contract HK/2009/02, and concreting works was conducted on 08 and 22 June 2017 under Contact HK/2009/02, non WDII-CWB Projects construction works was observed on 31 May 2017 and 08, 13, 22 and 26 June 2017 during monitoring period and observed as the major noise contribution. Hence, the exceedances were considered as non-Project related.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.1.5       No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

6.1.6.     Three limit level exceedances were recorded at M6 ¡V HK Baptist Church Henrietta Secondary School on 08, 16 and 19 June 2017 in this reporting month.

6.1.7.     Despite lifting works by crane and falsework erection works were conducted on 08 and 19 June 2017 respectively, no construction activity was conducted on 16 June 2017 and traffic noise was observed as the major noise contribution on 08, 16 and 19 June 2017. Hence, the exceedances were considered as non-Project related.

Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V Tunnel (Slip Road 8 Section)

6.1.8.     No exceedance was recorded in the reporting month.

 

6.2          Air Monitoring

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

6.2.1       There was one limit level of 1hr TSP monitoring recorded at monitoring station CMA5b on 3 June 2017.

6.2.2       No construction works was undertaken around the monitoring location on 3 June 2017 and no particular observation regarding air quality impact observed during sampling. Nevertheless, non WDII-CWB Project construction activities and traffic was observed opposite to the monitoring station was observed on 3 June 2017. In addition, it was further observed that garden and sweeping works conducted directly at the monitoring station by Pedestrian Plaza management office could potentially contribute to the elevated particulates level in the vicinity of the monitoring equipment. In view of the above, the exceedance was considered to be non-project related and potentially contributed by localized ambient condition and non-construction activity around the monitoring station.

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)

6.2.3       No action or limit level exceedance was recorded in this reporting month.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.2.4       No action or limit level exceedance was recorded in this reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

6.2.5       There was one limit level of 1hr TSP monitoring recorded at monitoring station CMA1b on 3 June 2017.

6.2.6       No construction works was undertaken around the monitoring location on 3 June 2017 and no particular observation regarding air quality impact observed during sampling and dust mitigation measure including haul road and dusty surface maintained in dampened condition were generally implemented. In view of the above, the exceedance was considered to be non-project related and potentially contributed by localized ambient condition and other environmental factor.

 

Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West

6.2.7       There was one limit level of 1hr TSP monitoring recorded at monitoring station CMA5b on 3 June 2017.

6.2.8       Manhole installation was undertaken around the monitoring location on 3 June 2017 and no particular observation regarding air quality impact observed during sampling. Nevertheless, non WDII-CWB Project construction activities and traffic was observed opposite to the monitoring station was observed on 3 June 2017. In addition, it was further observed that garden and sweeping works conducted directly at the monitoring station by Pedestrian Plaza management office could potentially contribute to the elevated particulates level in the vicinity of the monitoring equipment. In view of the above, the exceedance was considered to be non-project related and potentially contributed by localized ambient condition and non-construction activity around the monitoring station.

 

Contract no. HY/2010/08 ¡V Central-Wanchai Bypass ¡V Tunnel (Slip Raod 8 Section)

6.2.9       No action or limit level exceedance was recorded in the reporting month.

 

6.3          Water Quality Monitoring

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

 

6.3.1        No action or limit level exceedance was recorded in this reporting month.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East 

 

6.3.2       No action or limit level exceedance was recorded in this reporting month.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

 

6.3.3       No action or limit level exceedance was recorded in this reporting month.

 

Contract no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

 

6.3.4       No action or limit level exceedance was recorded in this reporting month.

 

Contract no. HK/2012/08- Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

 

6.3.5       No action or limit level exceedance was recorded in this reporting month.

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

 

6.3.6       There was 2 limit level of turbidity exceedances and 1 action level of suspended solid exceedance recorded at monitoring station C7 on 21 June 2017.

6.3.7       Removal of seawall block opposite to the monitoring location was conducted during the monitoring period on 21 June 2017 and turbid dispersion was observed generated from the works area and affecting the water quality at the concerned Windsor House cooling water intake during monitoring sampling.

6.3.8       As such, it was considered that turbidity and suspended solid exceedances were related to Project works and the Contractor was immediately advised to take immediate action to rectify the defects observed and conduct a remediation plan on checking the water holding tank and silt screen installed at the concerned monitoring location to ensure the water quality of the concerned location would not be adversely affected.

6.3.9       Rectification measures including reinstatement of deployed impermeable barriers and silt curtain, conducting cleaning and inspection of silt screen and silt curtain at the concerned water intake location at implement water flushing at the concerned water intake storage tank were observed implemented by 23 June 2017. Additional monitoring in accordance with the Event and Action Plan was conducted on 22 June 2017 and limit level exceedance of water turbidity was recorded. No further turbidity exceedance was recorded on the subsequent monitoring conducted on 23 June 2017, and no further suspended solid exceedance was recorded on the subsequent monitoring on 23 June 2017.

6.3.10    There was 1 limit level of turbidity exceedance recorded at monitoring station C7 on 23 June 2017.

6.3.11    After checking with the Contractor, despite D-wall excavation at TS3E was conducted on the monitoring date, Contractor mitigation measures such as deployment of impermeable barriers and silt curtain was generally in order, and the installed silt screen at the concerned water intake location was generally in order. No particular observation regarding water quality impact was observed during monitoring sampling period. In view of the above, it is considered that there was no information to suggest the exceedance was related to Project works.

6.3.12    There was 1 limit level of turbidity exceedance and 1 action level of suspended solid recorded at monitoring station C7 on 26 June 2017.

6.3.13    Underwater excavation at TS3E was conducted during the monitoring period on 26 June 2017. Owing to the malfunctioning of seawater pump on 26 June 2017 flood tide, fresh water was directly supplied to the storage holding tank for water supply to Windsor House Intake. Subsequently, during the sampling event on 26 June 2017 during ebb tide, turbidity and suspended solid exceedances were recorded at the water holding tank and hence it was considered potential contamination within water holding tank with direct freshwater supply by Project works site and affecting the water quality at the concerned Windsor House cooling water intake.

6.3.14    As such, it was considered that the turbidity and suspended solid exceedances were related to Project works and the Contractor was immediately advised to take immediate action to rectify the water quality concerned observed and prepare a remediation plan according to the Event and Action Plan to address the water quality concern. Remedial measures including reflushing the concerned water intake location were implemented on 27 June 2017. Additional monitoring in accordance with the Event and Action Plan was conducted on 27 June 2017 and no further turbidity exceedance was recorded. No further suspended solid exceedance was recorded on the subsequent monitoring on 28 June 2017.

 

6.4          Review of the Reasons for and the Implications of Non-compliance

6.4.1       There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.4.2       There was 2 limit level of turbidity exceedances and 1 action level of suspended solid exceedance recorded at monitoring station C7 on 21 June 2017. Removal of seawall block opposite to the monitoring location was conducted during the monitoring period on 21 June 2017 and turbid dispersion was observed generated from the works area and affecting the water quality at the concerned Windsor House cooling water intake during monitoring sampling. As such, it was considered that turbidity and suspended solid exceedances were related to Project works.

6.4.3       There was 1 limit level of turbidity exceedance and 1 action level of suspended solid recorded at monitoring station C7 on 26 June 2017. Underwater excavation at TS3E was conducted during the monitoring period on 26 June 2017. Owing to the malfunctioning of seawater pump on 26 June 2017 flood tide, fresh water was directly supplied to the storage holding tank for water supply to Windsor House Intake. Subsequently, during the sampling event on 26 June 2017 during ebb tide, turbidity and suspended solid exceedances were recorded at the water holding tank and hence it was considered potential contamination within water holding tank with direct freshwater supply by Project works site and affecting the water quality at the concerned Windsor House cooling water intake. As such, it was considered that the turbidity  and suspended solid exceedances were related to Project works

6.5          Summary of action taken in the event of and follow-up on non-compliance

6.5.1       Immediate report in-situ measurement has confirmed the exceedance recorded at C7 on 21 June 2017. The Contractor was immediately advised to take immediate action to rectify the defects observed and conduct a remediation plan on checking the water holding tank and silt screen installed at the concerned monitoring location to ensure the water quality of the concerned location would not be adversely affected. Rectification measures including reinstatement of deployed impermeable barriers and silt curtain, conducting cleaning and inspection of silt screen and silt curtain at the concerned water intake location at implement water flushing at the concerned water intake storage tank were observed implemented by 23 June 2017. Additional monitoring in accordance with the Event and Action Plan was conducted on 22 June 2017 and limit level exceedance of water turbidity was recorded. No further turbidity exceedance was recorded on the subsequent monitoring conducted on 23 June 2017, and no further suspended solid exceedance was recorded on the subsequent monitoring on 23 June 2017.

6.5.2       Immediate report in-situ measurement has confirmed the exceedance recorded at C7 on 26 June 2017. The Contractor was immediately advised to take immediate action to rectify the water quality concerned observed and prepare a remediation plan according to the Event and Action Plan to address the water quality concern. Remedial measures including reflushing the concerned water intake location were implemented on 27 June 2017. Additional monitoring in accordance with the Event and Action Plan was conducted on 27 June 2017 and no further turbidity exceedance was recorded. No further suspended solid exceedance was recorded on the subsequent monitoring on 28 June 2017.

7.         Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011 and no Project-related exceedance was recorded for air and noise monitoring.  It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area include road and drain works, backfilling works and reinstatement of Culvert and Cooling mains and installation of irrigation piping at P1 road were performed in June 2017 reporting month. As no project related exceedance were recorded during the reporting period, cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was considered as insignificant.

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities under Wan Chai Development Phase II were, road and drains construction, tunnel construction and backfilling works at Wan Chai West and Wan Chai East. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were drainage works and ventilation building construction at Central; temporary reclamation removal works at Causeway Bay, road works and side wall construction at Victoria Park; bridge construction, piling works, foundation works and building construction at North Point area in the reporting month. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan Chai North and North Point area.

7.0.5.     No significant air impact from construction activities was anticipated in the reporting month. Besides, no project related exceedance was recorded during the air and noise environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

8.         Environmental Site Audit

8.0.1.     During this reporting month, weekly environmental site audits were conducted for Contracts no.  HK/2009/01, HK/2009/02, HY/2009/15, HY/2009/19, HK/2012/08 and HY/2010/08. No non-conformance was identified during the site audits.

8.0.2.     Four site inspections for Contract no. HK/2009/01 were conducted on 31 May 2017, 7, 14 and 21 June 2017 in reporting month. There was no particular findings observed in this reporting month.  

8.0.3.     Four site inspections for Contract no. HK/2009/02 were carried out on1, 7, 15 and 20 June 2017 in reporting month. Results of these inspections and outcomes are summarized in Table 8.2.

     Table 8.2      Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Outcome

170615_01

15 Jun 2017

Drip tray shall be provided for oil and chemical containers at Portion 3&4.

The oil and chemical containers were removed on site.

Completion as observed on 20 June 2017

170620_01

20 Jun 2017

Chemical containers at Portion 5 shall be provided with proper labelling and stored properly at appropriate storage area.

Chemical containers were removed on site.

Completion as observed on 29 July 2017.

8.0.4.     Four site inspections for Contract no. HY/2009/15 were carried out on 29 May 2017, 6, 15, and 20 June 2017 in this reporting month. There was no particular findings observed in this reporting month.

 

8.0.5.     Four site inspections for Contract no. HY/2009/19 were carried out on 31 May 2017, 7, 14 and 21 June 2017 in reporting month. Results of these inspections and outcomes are summarized in Table 8.4.

Table 8.4 Summary of Environmental Inspections for Contract no. HY/2009/19

Item

Date

Observations

Action taken by Contractor

Outcome

170607_1

7 Jun 2017

Watering shall be provided more frequently to haul road to avoid dust emission (Portion 3)

Watering was provided to haul road to avoid dust emission

Completion as observed on 14 June 2017

170607_2

7 Jun 2017

The contractor shall properly follow-up with the provision / arrangement for movable noise barrier (Opposite to Habour Grand Hotel)

Contractor provide relevant information for further review and comment

Completion as observed on 21 June 2017

170614_1

14 Jun 2017

Contractor shall critically review the operation and treatment capacity of water treatment unit to ensure the discharge quality (Watson Road)

Additional water treatment unit was deployed

Completion as observed on 28 June 2017

8.0.6.     Four site inspections for Contract no. HK/2012/08 were carried out on 31 May 2017, 6, 13 and 20 June 2017 in this reporting period. Results of these inspections and outcomes are summarized in Table 8.5.

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2012/08

Item

Date

Observations

Action taken by Contractor

Outcome

170606_01

6-Jun-17

Water spraying shall be implemented on dusty ground surface for dust suppression at Zone A2

Water spraying has implemented and the ground was observed wet.

Completion as observed on 13 June 2017

170613_01

13-Jun-17

Bunding shall be provided along the culvert L structure alignment to prevent potential surface runoff from site.

Bunding was provided at the concerned location.

Completion as observed on 20 June 2017

 

8.0.7.     Four site inspections for Contract no. HY/2010/08 were carried out on 31 May 2017, 9, 14 and 21 June 2017 in this reporting period. Results of these inspections and outcomes are summarized in Table 8.6.

Table 8.6     Summary of Environmental Inspections for Contract no. HY/2010/08

Item

Date

Observations

Action taken by Contractor

Outcome

170531_1

31 May 2017

Impermeable barrier shall be tighten and deployed the extension to the seabed (TS3 South West)

Impermeable barrier was tighten and deployed the extension to the seabed

Completion as observed on 9 June 2017

170609_1

9 Jun 2017

Impermeable barrier shall be deploy and enclose the underwater excavation (-4 to -7mpD) to avoid potential contamination to nearby water (TS3 South West)

Impermeable barrier was deployed to enclose the underwater excavation area

Completion as observed on 14 June 2017

170614_1

14 Jun 2017

Damaged embankment shall be repair to avoid surface runoff (TS3)

Damaged embankment was repaired to avoid surface runoff

Completion as observed on 21 June 2017

170621_1

21 Jun 2017

Silt curtain shall be tighten and enclose the seawall block lifting works to avoid muddy dispersion (TS3)

No further seawall lifting works was observed

Completion as observed on 28 June 2017

170621_2

21 Jun 2017

Piping shall be disconnect and ensure the discharge follow the discharge license condition (TS3)

The concerned piping was disconnected

Completion as observed on 28 June 2017

 

9. Complaints, Notification of Summons and Prosecution

9.0.1.     There was no environmental complaint received in this reporting month.

9.0.2.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.3.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

 

Table 9.1 Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (Mar 2010) to last reporting month

47

June 2017

0

Total

47

 

Table 9.2 Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

10.       Conclusion

10.0.1.   The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.   The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1.

Table 10.1     Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HK/2009/01

¡P         Nil

¡P         Nil

HK/2009/02

¡P         Nil

 

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly.

¡P         Implement silt curtain in accordance with the associated plans submitted to EPD.

HY/2009/15

¡P         Nil

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

¡P         Implement silt curtain in accordance with the associated plans submitted to EPD.

HY/2009/19

¡P         Nil

 

¡P         Nil

HK/2012/08

¡P         Construction of Box 1 unit

 

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         To space out noisy equipment and position as far as possible from sensitive receiver.

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

HY/2010/08

¡P         Diversion pipe maintenance

¡P         Diaphragm Wall Removal Works

¡P         Removal of reclamation at TS3E and TS3W

 

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly